How Long Does a Kitchen Remodel Take in Los Angeles?
A kitchen remodel takes months, not weeks, once planning is counted. Houzz's 2026 survey of more than 20,000 U.S. homeowners found kitchens averaged 9.5 months of planning and 5.8 months of construction. A same-layout Los Angeles kitchen can build faster, and cabinet delivery, countertop fabrication and inspections set the pace.
How many months does a kitchen remodel really take?
Longer than most people budget for. Houzz's 2026 Houzz and Home study, fielded from January to March 2026 with more than 20,000 U.S. respondents, found that kitchens had the longest timeline of any room. As reported by the IWF trade show's news desk, the average was 9.5 months of planning and 5.8 months of construction.
Those are national averages across every size of project, from a counter swap to a gutted room with a moved wall. They are not Los Angeles numbers, and we found no dated local survey of kitchen durations. Use them as a ceiling for expectations: 5.8 months x 4.33 weeks is about 25 weeks of construction. A kitchen that keeps its layout should come in well under that. A kitchen that loses a wall may not.
What has to be finished before demolition day?
Three things: a drawn layout, a complete list of selections, and orders placed for anything with a wait. Cabinets are the longest wait in most kitchens. We did not find a manufacturer's published lead time we could verify, so we do not print one. Ask your supplier for the ship date in writing on the day you order, and plan demolition backward from it.
Choosing between new boxes and new doors changes this step, and our guide to cabinet refacing versus replacing covers that decision. The countertop choice matters less for timing, because slabs are measured only after the cabinets are set. Our kitchen remodeling page lists what a written proposal should name before any order is placed.
- Layout drawn and dimensioned, with appliance model numbers.
- Cabinets ordered, with a written ship date.
- Sink, faucet, hood, lighting and tile chosen and in stock or on order.
- Permit issued and posted at the job.
- A place set up to cook and wash dishes while the room is closed.
How long does the LADBS permit add to the schedule?
For a same-layout kitchen, very little. LADBS Information Bulletin P/GI 2026-003, effective January 1, 2026 and revised June 10, 2026, lists a residential kitchen remodel with no structural changes as an Express Permit, which is issued without plan check. The department's homeowner guide says Express Permits can be obtained online through its e-permit program.
A kitchen with structural work goes to plan check instead. LADBS describes its Regular Plan Check in loose terms: plans are assigned within a few days of submittal and returned within weeks depending on workload, and paying 50 percent more of the plan check fee buys an expedited review. If your design opens a wall, read our post on removing a kitchen wall before you set a start date. The permit types themselves are covered in our kitchen remodel permits guide.
These are City of Los Angeles rules. Glendale, Pasadena, Burbank and Santa Monica run their own building departments with their own review times.
A worked example: a same-layout kitchen, week by week
This is an illustration with stated assumptions, not a promise. Assume the cabinet supplier quotes 8 weeks from order to delivery, and the countertop fabricator needs 2 weeks from template to installation. Replace both with the written numbers on your own job. Cabinets land in week 5 below, so the order must be placed 8 - 4 = 4 weeks before demolition starts.
- Week 1: floors protected, old cabinets, counters and appliances removed, walls opened where pipes or wires change.
- Week 2: rough plumbing, electrical and any gas work, plus the hood duct.
- Week 3: rough inspection, then insulation and drywall to close the walls.
- Week 4: drywall finishing, primer, and flooring if it runs under the cabinets.
- Week 5: cabinets delivered and set, then the countertop template is made.
- Weeks 6 and 7: slabs are fabricated off site while painting and light fixtures go in.
- Week 8: countertops, sink, faucet and appliances installed.
- Week 9: backsplash tile, hood, finish electrical, final inspection and the punch list.
Nine weeks of construction plus four weeks of waiting on cabinets is 13 weeks from order to finish, about half of the 25-week national average.
Which inspections stop work, and for how long?
Two matter most in a kitchen: rough and final. The LADBS homeowner guide to permits and inspections says to call for the rough inspection when framing is complete and the plumbing piping, electrical wiring and heating ducts are installed, but before any of it is covered. That means drywall waits for the inspector. The guide asks for at least 24 hours of notice and warns that office workloads occasionally add another 24 hours.
The final inspection comes when construction is complete and all electrical and plumbing fixtures are installed. Interior painting does not need to be finished for it, according to the same guide. If the inspector finds a problem, a correction notice is left on site, the item is fixed, and the inspection is called again.
What usually makes a kitchen remodel run late?
Late decisions and late materials, far more often than slow labor. A faucet chosen after the plumber has finished rough-in can mean opening the wall again. A cabinet that arrives damaged restarts part of the supplier's clock, and the countertop template cannot be made until every base cabinet is fixed in place.
Older houses add their own surprises. In a home built before 1978, the EPA's Renovation, Repair and Painting rule requires paid firms that disturb painted surfaces to be certified and to use lead-safe work practices, which adds setup and cleanup time to demolition. Plan changes cost time too. The LADBS guide says that varying from approved plans during construction requires re-approval, so a mid-job decision to move the range is a permit event and not only a pricing one.
Can you live in the house while the kitchen is torn out?
Most households do, with a temporary kitchen in another room. The dusty stretch is short: demolition, and later the sanding of drywall. If new flooring or a full interior painting job is planned for the same visit, the work area grows and so does the disruption, which is the usual reason families leave for a week.
Noise has legal hours in the City of Los Angeles. The LADBS homeowner guide lists construction noise as allowed Monday through Friday between 7:00 am and 9:00 pm, and on Saturdays and national holidays between 8:00 am and 6:00 pm, with none on Sundays.
What should the schedule in your contract say?
Dates, in writing. The Contractors State License Board's page on home improvement contracts says the contract must provide a date of completion, state who will get the permits, and include a detailed written payment schedule in which payments do not exceed the value of work performed. Changes to price or scope need a written change order signed before the change is made.
A useful schedule ties payments to visible milestones: rough inspection passed, cabinets set, countertops installed, final inspection signed. The permit has its own clock. LADBS says a permit expires if work does not start within six months of issue, and two years after issue if the work is unfinished.
On our projects the calendar is the general contractor's job. MDG Builders, CSLB #1040337, orders the long-wait items, books the licensed plumbing, electrical, cabinet and tile subcontractors in sequence, and calls the inspections. For work inside the city, start with our Los Angeles kitchen remodeling page. In a city with its own building department, such as Glendale, the sequence is the same and the permit office is different. Budget questions are answered in our kitchen remodel cost guide.
Kitchen timeline questions
How long will a kitchen remodel take from start to finish?
Plan on several months in total. Houzz's 2026 national survey found kitchens averaged 9.5 months of planning and 5.8 months of construction. A kitchen that keeps its layout and has every material ordered before demolition can build in far less time, and the cabinet ship date is the number that decides it.
What order should you remodel a kitchen in?
Work from the inside of the walls outward. The usual order is demolition, rough plumbing, electrical and gas, the rough inspection, drywall, flooring if it runs under cabinets, cabinets, countertop template and installation, backsplash, fixtures and appliances, then the final inspection. Drywall cannot go up until the rough inspection is passed.
Should I move out during a kitchen remodel?
Usually not for a kitchen alone. Most households stay and set up a temporary kitchen with a refrigerator, microwave and a sink in another room. Moving out makes sense when floors and painting through the house are done at the same time.
How long does it take to get a kitchen remodel permit in Los Angeles?
A same-layout kitchen can be permitted quickly, because LADBS lists a residential kitchen remodel with no structural changes as an Express Permit issued without plan check. Structural changes go to plan check, which LADBS says is returned within weeks depending on workload. The department publishes no fixed number of weeks.
How long after cabinets are installed do countertops go in?
Expect a gap, because stone and quartz tops are measured only after the base cabinets are fixed in place. The fabricator makes a template, cuts the slabs in a shop and returns to install them. Ask your fabricator for the template-to-install time in writing, since it varies by shop and season.
What hours can contractors work on my kitchen in Los Angeles?
Construction noise is allowed Monday through Friday from 7:00 am to 9:00 pm and on Saturdays and national holidays from 8:00 am to 6:00 pm, with none on Sundays, according to the LADBS homeowner guide. Other cities set their own hours, so check with your building department outside the City of Los Angeles.
Work that goes with this

Kitchen Remodeling
Cabinets, counters, layout changes, permits and a written schedule, with prices tied to named sources.
See kitchen remodeling →
Flooring
Hardwood, engineered wood, vinyl plank, laminate and tile, with slab testing and a written scope.
See flooring →
Painting
Interior, exterior, stucco and cabinet painting with real prep, lead-safe rules followed and a written scope.
See painting →Keep reading

Do You Need a Permit for a Kitchen Remodel in Los Angeles?
Which kitchen changes get an LADBS Express Permit, which go to plan check, what the 2025 Energy Code adds, and what we could not confirm.
Read the guide →Cabinet Refacing vs. Replacing: Which Makes Sense for Your Kitchen?
Refacing or new cabinets: dated price ranges, a 25-linear-foot example, when each works, and California permit and contract rules.
Read the guide →
How Much Does a Kitchen Remodel Cost in California?
Sourced Los Angeles kitchen remodel prices for 2025 and 2026, why they disagree, and how to read a bid line by line.
Read the guide →Ready to plan your project?
Call or send the form. We schedule a site visit and send a written proposal.