Mechanics Lien Release Forms in California: Which of the Four to Use
California law provides four lien release forms: conditional and unconditional, each for a progress payment or a final payment. Collect a conditional release before you pay and an unconditional release after the payment clears, from the contractor and from every subcontractor and supplier that sent you a preliminary notice. The forms are in Civil Code sections 8132 to 8138.
What is a mechanics lien, and who can put one on your house?
A mechanics lien is a claim recorded with the county recorder against your property by someone who helped improve it and was not paid. Civil Code section 8400 gives the right to the direct contractor, meaning the one you signed with, and to subcontractors, material suppliers, equipment lessors, laborers and design professionals.
The warning that state law requires in every home improvement contract is blunt: even if you pay your contractor in full, unpaid subcontractors, suppliers and laborers may record liens and sue to foreclose. The Contractors State License Board says the owner is ultimately responsible for payment, which can mean paying twice. Lien releases are the paperwork that closes that gap, on a kitchen remodel as much as on new construction.
What is a 20-day preliminary notice, and why should you keep every one?
It is your list of who can lien. Under Civil Code section 8200, a subcontractor or supplier must give the owner a preliminary notice before it can record a lien. Section 8204 sets the timing: not later than 20 days after the claimant first furnished work. A late notice still counts, but it only protects work done from 20 days before the notice onward.
Two groups do not send one. A laborer is exempt, and a contractor with a direct contract with you has to notify only a construction lender, if there is one. So silence from your general contractor is normal, and a notice is not a lien. Save each one with the date it arrived, because each sender is someone whose release you will want.
What are the four lien release forms in California?
The statute supplies the wording, and Civil Code section 8124 says a release is effective only if it is substantially in the statutory form and signed by the claimant. The CSLB posts printable copies on its lien release forms page.
- Conditional Waiver and Release on Progress Payment, section 8132: for a claimant not yet paid. It names the check, takes effect only when that check is paid, and covers work through a stated Through Date.
- Unconditional Waiver and Release on Progress Payment, section 8134: signed after a progress payment is received. It states the amount and releases rights through the Through Date with no condition.
- Conditional Waiver and Release on Final Payment, section 8136: like the first form, for the last payment, covering the whole job once the check is paid.
- Unconditional Waiver and Release on Final Payment, section 8138: states that the claimant has been paid in full, which ends that claimant's lien rights on your job.
Conditional or unconditional: which release do you collect, and when?
Both, in sequence. With the invoice, you receive conditional releases for the amount about to be paid. You pay. Once the check has cleared, you receive unconditional releases for that same payment before the next one is due.
The conditional form protects the person signing it, since it has no effect until the money arrives. The unconditional form protects you, and it carries a bold notice that it is enforceable against the signer even if they have not been paid. That is why a subcontractor should not be asked to sign one early. For a conditional release, section 8124 requires evidence of payment: the claimant's endorsement on a check the bank has paid, or a written acknowledgment.
Business and Professions Code section 7159.5 says that after any payment, and before any further payment, the contractor shall, if requested, furnish a full and unconditional release from any potential lien claimant for the work paid for, and that the owner may withhold all further payments until those releases are furnished. The words if requested matter, so ask in writing at the start, ideally while you are still choosing a general contractor in Los Angeles.
A release signed only by your general contractor does not release the subcontractors and suppliers. Each claimant signs its own.
A worked example: releases on the second payment of an addition
Picture a $60,000 room addition. The second progress payment is $18,000, due when framing passes inspection. You have preliminary notices from two senders: the framing subcontractor and the lumber yard. The contractor's invoice breaks the payment down as $9,500 to the framer, $4,200 to the lumber yard and $4,300 for the contractor's own work and overhead. Check the sum: 9,500 + 4,200 + 4,300 = 18,000.
Before paying, you collect three conditional progress releases, one from each. One method the CSLB calls the simplest way to prevent liens is the joint check: $9,500 payable to the contractor and the framer together, $4,200 payable to the contractor and the lumber yard together, and $4,300 to the contractor alone. Both names must endorse a joint check.
Before the third payment, you collect three unconditional progress releases showing $9,500, $4,200 and $4,300 received. If the count of unconditional releases does not match the count of conditional ones, you hold the next check and ask why.
How long does a contractor or supplier have to record a lien?
The clock starts at completion. Under Civil Code section 8412, a direct contractor must record within 90 days after completion of the work of improvement. Section 8414 gives subcontractors and suppliers the same 90 days. An owner can shorten both by recording a notice of completion, which section 8182 allows on or within 15 days after completion. Once that notice is recorded, the direct contractor has 60 days from it and everyone else has 30.
On a calendar: a job completed on March 2 leaves lien rights open until May 31, which is 90 days later. If the owner records a notice of completion on March 12, subcontractors and suppliers have until April 11 and the direct contractor until May 11. The notice is recorded with the recorder of the county where the property sits, so Los Angeles County for a house in Pasadena and Orange County for one in Irvine. Ask the recorder's office or an attorney before relying on the shorter deadlines.
What do you do if a lien has already been recorded?
Read the dates before anything else. Under Civil Code section 8460, the claimant must file a court action to enforce the lien within 90 days after recording it. If none is filed in that time, the lien expires and is unenforceable, although the CSLB notes it stays in the county records until removed.
If you need clear title right away, section 8424 lets an owner or contractor record a lien release bond for 125 percent of the claim. For an $8,000 lien that is 1.25 x $8,000 = $10,000. The bond takes the lien off the property while the dispute continues. For an expired or invalid lien, the CSLB suggests a written demand by certified mail and then a court petition, where the court can order attorney fees paid. Hire a construction attorney for this step. Nothing in this article is legal advice.
What belongs in your job file?
MDG Builders, CSLB #1040337, is the direct contractor on its projects and hires licensed subcontractors for the trade work, so on our jobs the subcontractors and suppliers are the ones who send preliminary notices and sign releases. Ask us for those releases with each invoice. How a contractor answers that request is worth knowing before you hire, as our guides to how general contractors use subcontractors and reading a remodeling contract explain. A larger build such as an ADU simply has more names on the list.
- The signed contract with its payment schedule and the list of subcontractors and suppliers.
- Every preliminary notice, marked with the date received.
- A conditional release for every claimant on every payment, then the unconditional release that replaces it.
- Copies of cleared checks, front and back.
- The final unconditional releases and, if you record one, the notice of completion.
Lien release questions
What is the difference between a conditional and an unconditional lien release?
A conditional release takes effect only when the named payment is actually received, so it is signed before payment. An unconditional release states that payment has been received and gives up lien rights with no condition. California's forms are in Civil Code sections 8132 through 8138.
Can a subcontractor put a lien on my house if I paid the general contractor?
Yes. The lien warning required in California home improvement contracts says unpaid subcontractors, suppliers and laborers may record liens even if you paid your contractor in full. A subcontractor or supplier must first have given you a preliminary notice, which is why you keep those notices.
Do lien releases need to be notarized in California?
The statutory forms do not include a notary block. Civil Code section 8124 requires that a release be substantially in the statutory form and signed by the claimant, and a conditional release also needs evidence of payment. Your lender or title company may ask for more.
How long does a mechanics lien last in California?
A claimant has 90 days after recording the lien to file a court action to enforce it. Under Civil Code section 8460, a lien with no action filed in that time expires and is unenforceable, unless a recorded extension of credit applies.
Is a preliminary notice the same as a lien?
No. A preliminary notice only tells you that the sender is working on or supplying your project and could record a lien if unpaid. It is due within 20 days after that sender first furnished work, and it tells you whose releases to collect.
Can I withhold payment until I get a lien release?
Yes, for further payments. Business and Professions Code section 7159.5 says that after you pay, the contractor must furnish unconditional releases on request for the work paid for, and you may withhold all further payments until they arrive.
Work that goes with this

Room Additions
Family rooms, primary suites and second stories, from zoning check to final inspection, with sourced prices.
See room additions →
Kitchen Remodeling
Cabinets, counters, layout changes, permits and a written schedule, with prices tied to named sources.
See kitchen remodeling →
ADU Construction
Garage conversions, detached ADUs and JADUs, with the 2026 permit clocks, utilities and sourced costs explained.
See ADU construction →Keep reading
How to Read a Remodeling Contract in California, Page by Page
The headings state law requires in a home improvement contract: price, down payment, progress payments, dates, change orders and notices.
Read the guide →
How General Contractors Use Subcontractors
Why most general contractors hire specialists for the field work, what that means for you, and what to ask for in writing.
Read the guide →Home Improvement Contract Red Flags in California: 12 Warning Signs
Twelve warning signs in a contractor's pitch, payment terms and paperwork, each checked against CSLB guidance and California statute.
Read the guide →Ready to plan your project?
Call or send the form. We schedule a site visit and send a written proposal.